Second day:
La pelleteuse revient finaliser la surface de la couche d'argile qui est recouverte d'un géotextile. La surface utilisée avoisine les 250 m².
The excavator is back to finalize the clay layer surface which is then covered with a geotextile. The surface used is around 250sqm.
Photo E. Zander |
A slightly deeper lateral trench receives a drain pipe to control the amount of water in the soil.
Photo J. Ollivro |
Different networks (sewage, drainage, electricity and signals) have been either renewed or silghtly displaced.
Photo E. Zander |
Photo E. Zander |
A layer of 0/31,5 calibre gravel is poured and compacted for a final thickness of 10 cm.
Pendant ce temps là, le tronçon de voie du PN1 a été entièrement reconstitué.
In the meantime, the RC1 track portion has been entirely reconstructed.
Photo E. Zander |
The former classical "Vignole" rails have been replaced by double headed ones, welded directly on the steel sleepers. As they were buried, only a few original sleepers could be reused. Counter-rails have been added to the mounting to keep the wheels passage clear form soil. Spacers maintain the distance between the rails in reinforcement of the weldings.
Photo E. Zander |
A suivre...
To be continued...